Why 22 kV is the Singapore standard
Singapore's distribution network is built around three voltage tiers: 230/400 V (low tension), 6.6 kV (legacy, being phased out), and 22 kV (the modern distribution standard). Above 22 kV is sub-transmission at 66 kV and 230 kV — territory occupied by rail depots, very large industrial sites and the grid itself.
The reason a 22 kV intake is preferred for medium-to-large demand: at LT, the cables become impractically large above a few hundred amps. Stepping up to 22 kV brings the current down by a factor of about 55 and lets you serve megawatts of demand with sensibly-sized cables. The trade-off is the customer takes on a substation, switchgear, transformer and all the associated regulatory weight.
What's actually inside a 22 kV customer substation
A typical 22 kV / 0.4 kV customer substation includes the following components:
- SP incoming cable termination. The HT cable from SP arrives at the customer's cable end-box.
- 22 kV Ring Main Unit (RMU) or HT switchgear panel — typically SF6-insulated. Provides incoming switching, isolation and earthing, and outgoing switching to the transformer.
- Protection & metering. SP's metering on its side; customer's protection relays (overcurrent and earth fault) on the customer side.
- 22 kV / 0.4 kV transformer. Typically dry-type cast resin for indoor installation, vector group Dyn11, impedance around 6% for a typical distribution transformer. Rating sized to the diversified load with appropriate margin.
- LV switchboard. Main switchboard immediately downstream of the transformer. Houses the LV main incomer, busbar, outgoing feeders, capacitor bank if used.
- Earthing system. Separate or combined earthing electrodes for HT, LV neutral, equipment earth.
- Auxiliary supplies. Substation lighting, ventilation fans, control supplies, small power.
- Control panel. Annunciator, alarm interfaces, SCADA tie-ins if applicable.
- Cable trays and trunking. Segregated HT, LV and control routes.
The substation room — what it has to provide
The substation room is part of the building works and must satisfy a long list of requirements from SP and from BCA / SCDF:
- Floor area — sized to the equipment with clear maintenance access on all required sides. Typical small 22 kV substations are 40–60 m²; larger or dual-transformer rooms can be 100 m² or more.
- Floor loading — capable of supporting the transformer (multi-tonne) and the switchgear.
- Ceiling height — typically 3 m clear minimum to accommodate equipment and overhead cable management.
- Doors — large enough to admit the largest piece of equipment (usually the transformer) plus access doors for personnel; specified opening direction; with rated fire performance where required.
- Ventilation — sized to dissipate transformer heat losses; natural where possible, mechanical with fail-safe interlocks where required.
- Fire performance — fire-rated enclosure as per SCDF requirements; sometimes with smoke detection and CO₂ or alternative fire suppression.
- Flood resilience — raised floor / kerb to keep the substation above local flood level.
- SP access — independent access from a public road or fire engine access; security arrangements as specified.
- No services overhead — no water pipes, drainage or non-essential services routed above the substation room.
Protection & co-ordination
The 22 kV / LV protection scheme has to do three things simultaneously: (1) protect the equipment from fault damage; (2) protect personnel from arc flash and shock; and (3) co-ordinate with SP's upstream protection so that customer faults don't take out SP's network.
Typical protection scheme:
- 22 kV incomer protection — overcurrent (50/51) and earth fault (51N), often with sensitive earth fault.
- Transformer protection — primary side overcurrent, restricted earth fault, optionally differential protection on larger transformers, plus mechanical protections (Buchholz, oil temperature, winding temperature on oil-filled designs).
- LV main protection — main breaker with electronic trip unit, settings co-ordinated upstream and downstream.
- Selectivity study — time-current curves plotted; verifies that faults at any point trip only the nearest upstream device.
Submission cycle (where the design meets the regulator)
- SP application with single-line diagram, load schedule, substation room sketch.
- SP issues Conditions of Service Connection.
- PE-endorsed detailed design aligned to the Conditions.
- BCA submission of the substation room as part of the building works approval.
- SCDF submission for fire safety aspects of the substation room.
- Procurement, installation, T&C.
- SP energisation.
Common pitfalls
- Substation room positioned underneath habitable space. Acoustic and safety concerns; sometimes forces redesign.
- Insufficient transformer offloading space. Transformer maintenance requires room to wheel it out.
- Ventilation undersized. Transformer overheats; thermal trips during summer.
- Earthing electrodes installed late. Site congestion makes earth electrode work expensive and uncertain in fall-of-potential testing.
- Protection settings copied from another project. Co-ordination has to be specific to your network — there is no "standard" set of settings.
- LV switchboard built before the protection co-ordination is finalised. Forces switchboard modifications late.
Frequently asked questions
Can a 22 kV substation be located on an upper floor?
Yes, although ground floor or basement is more common for transformer access. Upper-floor substations need careful structural design (floor loading), transformer access route (lift or removable wall panel) and fire/flood considerations.
How big does the transformer need to be?
Sized to the diversified maximum demand with engineering margin — typical sizing factors range from 1.1× to 1.4× of MD depending on growth allowance and harmonic content. Avoid significantly oversizing — it costs more capital and runs at low efficiency.
Oil-filled or dry-type transformer?
For Singapore indoor distribution, cast-resin dry-type is the modern default — no fire/spill concerns, low maintenance. Oil-filled is still used for larger ratings or where supplied directly by SP.
Can we connect a generator in parallel?
Parallel-to-grid operation requires explicit SP approval, anti-islanding protection, and additional licensing under EMA's generation licence regime if above threshold. Most customer generators are emergency-only (closed transition or open transition, not parallel).